FERC calls for additional steps to minimize environmental impacts on the Rover Pipeline
Feb. 23--A federal agency has released a 450-page draft report assessing the impacts of a natural gas pipeline across northern
Ohio
, and the pipeline company must do more before receiving federal approval for the $4.2 billion Rover Pipeline.
The report was posted Friday by the Federal Energy Regulatory Commission that oversees interstate natural gas pipelines.
The commission, in its report, concluded that approving the pipeline "would have some adverse and significant environmental impacts."
But those impacts can be "reduced to acceptable levels" with mitigation plans advanced by the pipeline companies and with additional measures recommended by the FERC staff.
The agency is requiring "additional mitigation to minimize or avoid" impacts, the report says.
The major issues were linked to water bodies, wetlands, vegetation, wildlife habitat and alternatives, the report says.
The federal agency is accepting public comment on its report through April 11. Public hearings will be scheduled later.
The Rover Pipeline, advanced by
Dallas
-based Energy Transfer Partners, would be 510 miles long and extend into
Pennsylvania
and
West Virginia
. The main
Ohio
leg would be 204 miles and run to Defiance in northwest
Ohio
. It would cross parts of southern
Stark
and
Wayne
counties.
The
Wayne County
commissioners had opposed the project, saying it would damage
Ohio
farmland. It would also create a safety concern where public safety communication systems in the county are limited, the commissioners said last fall.
The project would require two pipes, both 42 inches in diameter. It would transport 3.25 billion cubic feet of natural gas per day. That's enough to heat 35,000 houses for one year.
The pipeline would extend north into
Michigan
and connect to existing pipelines and make natural gas from
Ohio's
Utica Shale available in the Midwest,
Ontario
and the Gulf Coast.
Proponents have said the Rover Pipeline would create as many as 6,500 construction jobs in
Ohio
. It would provide $124 million in
Ohio
for easements and another $135 million in local taxes.
Rover Pipeline LLC, an Energy Transfer Partners subsidiary, had initially hoped to have construction underway in 2016, but the project has been delayed by the federal review.
Bob Downing can be reached at 330-996-3745 or bdowning@thebeaconjournal.com.
___
(c)2016 the Akron Beacon Journal (Akron, Ohio)
Visit the Akron Beacon Journal (Akron, Ohio) at www.ohio.com
Distributed by Tribune Content Agency, LLC.
DISCLOSURE: The views and opinions expressed in this article are those of the authors, and do not represent the views of equities.com. Readers should not consider statements made by the author as formal recommendations and should consult their financial advisor before making any investment decisions. To read our full disclosure, please go to: http://www.equities.com/disclaimer